Pump Station # 1 Progress

Pictures of your tax dollars at work: Construction is progressing at the storm water pump stations. Back-up, emergency operation gates are installed and operational at Pump Station No. 2. Two of the new back-up, emergency operation gates and actuators are installed at Pump Station No. 1. The associated electrical work at Pump Station No. 1 is also underway. These projects are financed with our bonds.

Pump Station to Serve Forest Green Area

This project is a new storm water pump station to serve the Forest Green neighborhood. This area currently drains to the detention pond only by a gravity pipe. This new pump system will accommodate approximately 13.7 inches of rainfall in 24 hours with the pump station and storage volume. Status: Under Construction, anticipated completion of late January 2020.

Your tax dollars at work: